Concrete Substrate Must meet the below requirement.
Bond failure occurs when the substrate concrete floor is not smooth or dry enough. Then the epoxy coats would fail, peel, break into chips or otherwise separates into pieces so that the concrete beneath is clearly visible.
Items | Content |
Concrete Flatness |
The maximum altitude difference of concrete floor within 2 meters long should be below 2mm. |
Concrete Strength | Weak strength of substrate will leave the paint layers off.General requirement on concrete strength should be ≥25Mpa |
Substrate Drying |
Moisture exists in concrete and mortar floor,which will reduce the bonding strength between paint and substrate,also will cause paint bubbles and delamination. Judgment Method: 1) Moisture content meter to check the substrate water content,which should be below 6%. 2) In method of ASTM4263,put thin plastic film at size 45cm×45cm to the substrate surface,and seal the 4 sides with adhesive tape. After 16 hours,if the water appears under the plastic or the substrate turns black,the substrate is not dry enough for paint. |
Attachments | On the surface of substrate concrete, cement dust usually are attached,especially newly finished concrete surface,there are always cement particle mortar in loose condition without strength. Rust stains on steel sheet. All of these attachments will affect the bonding power between paint and substrate.So they must be grinded and removed before paint. |
Environmental conditions |
1) The whole area must be sealed to prevent paint quality problems like impurity,sinkhole,spongy surface 2)Temperature should be between 10~35℃,Relative air humidity ≤75% |